An Ajman company needs a machine commissioned in six weeks. The engineer it wants to hire is outside the UAE. The company's production schedule says when the equipment should run, but the worker's lawful start date depends on the right work permit and entry record. If the installation slips, the project manager also needs to know what must be extended and who can approve it. The mission work permit exists for this sort of bounded overseas recruitment. The employer and worker should agree on the assignment, verify the approvals and plan how the engagement will end before booking travel. [1][2][3]

Choose the permit by the worker’s starting position

Article 6 of Cabinet Resolution No. 1 of 2022 distinguishes a mission work permit from the temporary work permit and part-time work permit. A ministry-registered establishment can use the mission category to bring a worker from overseas for a defined temporary job or project. The UAE Government describes the temporary work permit as a route for a worker already in the country who takes a time-limited assignment at another company and then returns to the original employer. A part-time permit concerns work with fewer hours or days than the corresponding full-time role. [1][2]

Starting position Route to check Question that helps classify the case
Candidate outside the UAE, named employer and defined project MOHRE mission work permit Which establishment will employ the person, and what work will end the assignment?
Worker already in the UAE with a current employer Temporary work permit, where applicable Who holds the current permit, and what approval applies to the second assignment?
Worker to be employed under a reduced-hours schedule Part-time work permit, where applicable Do the hours, contract and current status meet the requirements for this route?
Overseas candidate for an ongoing position Standard overseas recruitment work permit Is this an ordinary hire expected to continue after the first project?
Overseas supplier proposing to send its own employees Applicable employer, host and entry arrangement Who will employ and direct each worker in the UAE, and which authority can approve that arrangement?

A short purchase order does not establish the legal relationship with the person doing the work. Ask who will pay the worker, give instructions and accept the deliverable. If the person is already employed locally, begin with the CYUAE temporary work permit guide. If the defining feature is a reduced work schedule, compare the UAE part-time work permit route. [1][2]

Match the project, establishment and worker

The executive regulation requires a valid establishment licence without violations that suspend activity, an occupation consistent with the establishment's activity, and an application by its authorised signatory. The general minimum age for this route is 18. A regulated occupation also needs the qualifications or permission required by its competent authority. Start with the legal establishment that will appear on the application. A trade name, client purchase order or site address can identify a commercial relationship without identifying the employer. The Ajman mainland business guide explains why activity, premises and approvals should be checked together. [2]

Write a one-page scope with the role, worksite, start condition, target completion date and objective acceptance milestone. If the engagement crosses group companies or client premises, name each entity and explain its role before asking the ministry which party may submit. Verify any applicable electronic quota and whether a previous permit is still active. Those checks can change the route even when the worker has the required technical skills. The federal labour rules authorise MOHRE to withhold, refuse renewal of or cancel permits in specified situations, including submission of incorrect documents. [1][2]

The worker and authorised signatory should reconcile passport spelling, occupation and the agreed contract terms. Keep a usable passport copy, any required qualification or professional registration, and the signed offer or contract in the case file. The specific upload screen may retrieve some records electronically. MOHRE's work permit consultation described simpler digital processes. Confirm the current mission transaction fields and evidence requests in the ministry's channel for this application. The legal eligibility conditions still apply even where the system can retrieve a record without an upload. [2][6]

Track labour approval and immigration permission separately

There are two approvals to follow. MOHRE regulates the employment authorisation for a ministry-registered establishment. The Federal Authority for Identity, Citizenship, Customs and Port Security (ICP) handles the corresponding entry process for an Ajman case under the federal immigration system. Articles 18 and 19 of Cabinet Resolution No. 65 of 2022 provide for a work-mission entry visa with a UAE host. They require evidence of the temporary contractual relationship and purpose, health fitness and, where applicable, MOHRE approval. A tourist or general visit visa does not give a worker permission to start work. [2][3][5][7]

  1. Identify the employing establishment and record the overseas candidate's current status, occupation and proposed dates.
  2. Have the authorised signatory check the mission route, submit through the appropriate MOHRE channel and retain the reference. Resolve missing evidence before committing to travel or shifts.
  3. Coordinate the corresponding entry application with ICP. Confirm what the worker must provide and check that the passport details, host and purpose agree across the two records.
  4. Read the issued documents for entry and expiry dates. Brief the worker and the site manager on the approved task and retain the employment records that will support payroll and closeout.
  5. If travel changes, check the official records before assuming a new entry is possible. The UAE entry and exit movement guide explains what to verify when travel records need reconciliation. [2][3][5]

Budget the mission in separate lines

The amended fee schedule in Cabinet Resolution No. 37 of 2022 lists AED 50 for the overseas work permit application and AED 250 for issuing a mission work permit across the three establishment categories in its table. Read these as separate federal labour fee lines, and check the actual itemised bill before payment. Keep immigration fees, any applicable health checks, channel charges and travel costs separate in the budget. The labour law prohibits the employer from charging the worker recruitment and employment costs directly or indirectly. A request for a transfer to a personal account to release an offer is a reason to verify the file with the authority. [4][7][8]

Plan for a delay before it happens

Suppose the Ajman engineer starts with a six-week commissioning scope. A late replacement part pushes final testing into the following month. The employer should compare the revised schedule against three records: the agreed project or contract period, the MOHRE permit dates and the ICP stay dates. Where work is expected to continue past an authorised date, check extension eligibility early enough to leave time for approval. ICP says a work-mission visa based on MOHRE approval can be extended only once, subject to MOHRE approving the extension. An application receipt alone should not be treated as an updated authorisation. [2][3][5]

The immigration regulation also provides a separate two-year multiple-entry work-mission visa in Article 19 bis. It allows up to 60 continuous days and a maximum of 180 days' stay within one year, subject to the specified approvals and applicable eligibility controls. It requires a medical examination within 15 days of the first entry using that visa. It is a distinct category. A project involving repeated visits should verify that its particular establishment and occupation qualify before relying on it. [3]

Close the assignment and reconcile the records

Write down the final working date, confirm what payroll owes and resolve any permit or entry closeout with the responsible authority. Keep confirmation of the work performed, payment and any cancellation the case requires. The executive regulation's general work-permit cancellation procedure includes confirmation that the employer has granted the worker their entitlements. For a project that becomes an ongoing role, determine the correct new approval before extending the work beyond the existing authority. [2]

Frequently asked questions

Can a worker start as soon as the company gets an application reference?

Use the reference to track the case. Start work only after the required work and entry authorisations are in force, with the worker and activity covered by those records. [2][3][7]

Does the same approval let the worker return for a second visit?

Check the number of entries and the expiry on the actual immigration document before departure. Article 19 bis creates a separate multiple-entry route with its own controls. A return trip also requires a live work authorisation covering the assignment. [2][3]

Is the shorter project the only condition for eligibility?

No. The mission route also turns on overseas recruitment by an eligible establishment, a matching occupation and the applicable immigration and professional requirements. Ask the employer to identify the specific permit, issuing authority and job offer before accepting an assignment. [1][2][3]

Official sources and editorial method

Sources checked on 13 November 2026. Numbered references support the official facts stated. CYUAE labels hypothetical examples and editorial analysis in the text. The image caption records the photograph’s context, source and licence.

  1. UAE Government — Work permit types and the overseas mission route ↗
  2. UAE Legislation — Cabinet Resolution No. 1 of 2022, Articles 6–7 ↗
  3. UAE Legislation — Cabinet Resolution No. 65 of 2022, Articles 18–19 bis ↗
  4. UAE Legislation — Cabinet Resolution No. 37 of 2022 on MOHRE fees, Schedule 2 (Arabic) ↗
  5. ICP — Visa extension, including work-mission visas ↗
  6. MOHRE via Sharik — Developing Procedures to Access Work Permit Services ↗
  7. UAE Government — Tips to avoid labour and visa fraud ↗
  8. UAE Legislation — Federal Decree-Law No. 33 of 2021, Article 6 ↗